CAPM Practice: Determine how to conduct stakeholder communication

Question 14 of 67 in Determine how to conduct stakeholder communication

Pick an answer below — you'll get the explanation instantly, no signup.

What is the purpose of a 'communication plan' in a business analysis context?
Show answer & explanation

Correct answer: Defining what information needs to be communicated, to whom, when, and through which channels throughout the project

Explanation

A communication plan ensures intentional, systematic communication — preventing information gaps and overload. It specifies audiences, content, frequency, format, and responsible communicators for each type of communication.

**Why not A:** "Social communication rules" describes communication etiquette or norms, not a communication plan. A communication plan is a structured document that defines what information will be communicated, to whom, when, how, and by whom. Social rules may inform tone and style but are not the plan itself.

**Why not B:** "Marketing messages" narrows the scope to external promotional content, which is only one possible type of communication. A communication plan in project or business analysis context encompasses all stakeholder communications—status reports, requirement reviews, change notifications—not just marketing outreach.

**Why not C:** "Past communications for audit" describes a communication archive or log, not a communication plan. While maintaining records of past communications may be valuable for compliance or lessons learned, a communication plan is forward-looking, defining how future communications will be structured and delivered to stakeholders.

Key Concept

This question covers Determine how to conduct stakeholder communication under Determine how to conduct stakeholder communication (Business Analysis Frameworks).