CAPM Practice: Demonstrate an understanding of the various project life cycles and processes
Question 26 of 95 in Demonstrate an understanding of the various project life cycles and processes
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: A constraint, because it is a fixed limitation imposed on the project.
Explanation
This is a constraint—a limiting factor that restricts the project's options. The fixed deadline imposed by external regulatory requirements is a boundary condition the project must work within.
**Why not B:** An assumption is a factor accepted as true for planning purposes. While the team may assume they can meet the deadline, the statement itself is a fixed external requirement (regulatory deadline) that limits the project's flexibility, which defines a constraint.
**Why not C:** An issue is a current problem requiring immediate resolution. The December 31 deadline is not a problem; it is a known boundary condition that the project must work within. It does not require resolution; it requires compliance.
**Why not D:** While missing the deadline could indeed result in penalties, the statement itself describes a fixed limitation, not an uncertain event. The deadline is certain and imposed externally. The risk would be "the project may not meet the December 31 deadline," which is a separate consideration.
Key Concept
This question covers Demonstrate an understanding of the various project life cycles and processes under Demonstrate an understanding of the various project life cycles and processes (Project Management Fundamentals and Core Concepts).
All 1,500+ CAPM questions are free
Sign up to track your progress, see detailed analytics, and get personalized study recommendations.
Sign Up Free