CAPM Practice: Demonstrate an understanding of the various project life cycles and processes
Question 64 of 94 in Demonstrate an understanding of the various project life cycles and processes
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: 1. Harvest Market Co manages 12 simultaneous efforts including store renovations, a new loyalty program, and daily inventory replenishment → Portfolio 2. Echelon Tech coordinates three related projects: database migration, application upgrade, and user training to achieve a digital transformation → Program 3. Quartile Advisory is developing a custom financial reporting tool for a client over 8 months → Project 4. Resonance Creative runs its ongoing social media management service for multiple clients → Operations
Explanation
A project is a temporary endeavor to create a unique deliverable (custom tool). A program is a group of related projects managed together to achieve benefits (three coordinated projects for digital transformation). A portfolio is a collection of projects, programs, and operations managed as a group to achieve strategic objectives (12 simultaneous efforts). Operations are ongoing activities that sustain the business (recurring social media management).
**Why not A:** This option incorrectly classifies Harvest Market's 12 simultaneous efforts as operations and Resonance Creative's ongoing service as a portfolio. A mix of projects, programs, and operations managed together is a portfolio, and ongoing repetitive service delivery is operations.
**Why not C:** This option mismatches all four items. Harvest Market's 12 efforts are a portfolio, not a program; Echelon Tech's three related projects are a program, not a project; Quartile Advisory's 8-month tool is a project, not operations; and Resonance Creative's ongoing work is operations, not a portfolio.
**Why not D:** This option reverses all four classifications. Harvest Market's collection is a portfolio, not a project. Echelon Tech's coordinated projects are a program, not operations. Quartile's temporary engagement is a project, not a portfolio. Resonance Creative's ongoing service is operations, not a program.
Key Concept
This question covers Demonstrate an understanding of the various project life cycles and processes under Demonstrate an understanding of the various project life cycles and processes (Project Management Fundamentals and Core Concepts).