Question 63 of 94 in Demonstrate an understanding of the various project life cycles and processes

Pick an answer below — you'll get the explanation instantly, no signup.

Irina Reddy is reviewing the project scope for a marketing campaign at Resonance Creative. She notices the scope includes 'Increase brand awareness' but lacks specific deliverables or success criteria. What is the PRIMARY concern with this scope statement?
Show answer & explanation

Correct answer: It describes an outcome rather than defining specific deliverables and acceptance criteria

Explanation

Project scope should define specific deliverables and how success will be measured. 'Increase brand awareness' is a goal or outcome, but does not specify what will be delivered (e.g., social media content, events, advertisements) or measurable acceptance criteria (e.g., reach 50,000 impressions, 20% increase in survey recognition).

**Why not A:** The concern is not about marketing versus technical content. Scope statements for marketing projects are perfectly valid. The issue is that "increase brand awareness" is a vague outcome without specific deliverables or measurable success criteria.

**Why not C:** The scope may or may not be too ambitious — that cannot be determined without specific deliverables defined. The primary concern is that the scope describes an outcome without specifying what will actually be delivered and how success will be measured.

**Why not D:** While timeline and budget constraints are important project parameters, the primary concern with this scope statement is the absence of specific deliverables and acceptance criteria. Without knowing what will be delivered, timeline and budget discussions are premature.

Key Concept

This question covers Demonstrate an understanding of the various project life cycles and processes under Demonstrate an understanding of the various project life cycles and processes (Project Management Fundamentals and Core Concepts).

Share:

All 1,500+ CAPM questions are free

Sign up to track your progress, see detailed analytics, and get personalized study recommendations.

Sign Up Free