CAPM Practice: Demonstrate an understanding of the various project life cycles and processes
Question 11 of 94 in Demonstrate an understanding of the various project life cycles and processes
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: The upgrade is a project because it has a defined beginning and end to create a unique deliverable, while facility maintenance is ongoing operational work
Explanation
A project is temporary with a defined beginning and end, creating a unique product, service, or result. Operations are ongoing and repetitive to sustain the business. The system upgrade is temporary work to create a unique improvement, while regular maintenance is continuous operational work.
**Why not B:** The upgrade is not operations simply because it involves existing facilities. Operations refers to ongoing, repetitive work. The upgrade has a defined beginning and end with a unique deliverable, making it a project regardless of whether it touches existing infrastructure.
**Why not C:** The upgrade involves security systems that already exist, but it is creating a unique improvement with a defined timeline. Existing systems can be the subject of projects when the work is temporary and creates a unique result, such as an upgrade.
**Why not D:** Having a budget does not distinguish projects from operations. Both projects and operations require funding. The distinguishing factor is the temporary, unique nature of the upgrade versus the ongoing, repetitive nature of facility maintenance.
Key Concept
This question covers Demonstrate an understanding of the various project life cycles and processes under Demonstrate an understanding of the various project life cycles and processes (Project Management Fundamentals and Core Concepts).