CAPM Practice: Demonstrate an understanding of the various project life cycles and processes
Question 10 of 94 in Demonstrate an understanding of the various project life cycles and processes
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: 1. Program → Related projects managed together to obtain benefits not available from managing them individually 2. Portfolio → Projects grouped together to optimize resources and align with strategic objectives 3. Predictive approach → A development approach with defined scope, schedule, and cost determined early in the life cycle 4. Adaptive approach → An iterative approach that welcomes changing requirements throughout the project
Explanation
A program is a group of related projects managed in a coordinated way to obtain benefits and control not available from managing them individually. A portfolio is a collection of projects, programs, and operations managed as a group to achieve strategic objectives. Predictive (or plan-driven) approaches determine scope, time, and cost early with changes carefully managed. Adaptive (or change-driven) approaches use iterative cycles and welcome changing requirements even late in development.
**Why not B:** This option assigns the program definition to a development approach and the portfolio definition to an iterative approach, completely confusing organizational structures with delivery methodologies. Programs and portfolios are organizational groupings, not development approaches.
**Why not C:** This option incorrectly defines a program as an iterative approach and assigns the adaptive approach definition to related projects managed together. It mixes organizational hierarchy concepts with delivery methodology concepts by swapping these two definitions, even though the portfolio and predictive approach pairings are correct.
**Why not D:** This option assigns the portfolio definition to programs and the predictive approach definition to portfolios, while assigning the adaptive approach definition to the predictive approach and the program definition to the adaptive approach. None of the four matches correctly pair the term with its actual definition.
Key Concept
This question covers Demonstrate an understanding of the various project life cycles and processes under Demonstrate an understanding of the various project life cycles and processes (Project Management Fundamentals and Core Concepts).