CAPM Practice: Demonstrate an understanding of the various project life cycles and processes
Question 94 of 95 in Demonstrate an understanding of the various project life cycles and processes
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: The approval need is a constraint, and the potential for delays is a risk
Explanation
The regulatory approval requirement is a constraint because it is a limiting factor that restricts the project's options (testing cannot begin without it). The potential for delays is a risk because it is an uncertain event that, if it occurs, could have a negative impact on the project schedule.
**Why not A:** The potential for regulatory delays is not an assumption — it is a risk based on evidence from similar projects. An assumption would be an accepted belief taken as true without proof, such as assuming the approval will take exactly 3 weeks. The delay potential is an uncertain event with known probability.
**Why not B:** The regulatory approval requirement is not a risk — it is a definite constraint that the team must work within. Additionally, the potential for delays is a risk (uncertain future event), not an issue (a problem that has already occurred).
**Why not D:** The regulatory approval requirement is not an assumption — it is a documented constraint that restricts project options. An assumption would be something believed to be true without proof, while the approval requirement is a confirmed mandatory prerequisite.
Key Concept
This question covers Demonstrate an understanding of the various project life cycles and processes under Demonstrate an understanding of the various project life cycles and processes (Project Management Fundamentals and Core Concepts).