CAPM Practice: Demonstrate an understanding of project roles and responsibilities
Question 16 of 94 in Demonstrate an understanding of project roles and responsibilities
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Facilitator, by enabling the team to collaborate and reach their own resolution.
Explanation
Halima is acting as a facilitator by creating an environment where team members can collaborate and resolve issues themselves rather than imposing a solution. Facilitation involves guiding discussions and enabling the team to work through challenges collaboratively.
**Why not A:** Coaching focuses on developing team members' own capabilities, typically through questioning and feedback, and option A instead describes handing the team the correct technical solution. Halima is not providing guidance on the correct technical solution; she is enabling the team members to resolve the issue themselves through facilitated discussion.
**Why not B:** A negotiator bargains between opposing viewpoints to reach a compromise, often with the negotiator proposing solutions. Halima is not bargaining or proposing compromises; she is creating space for the team to collaborate and find their own resolution.
**Why not D:** A working member contributes technical expertise to produce deliverables. Halima is not contributing her own technical knowledge to solve the problem; she is guiding the process of discussion so the team can reach resolution collaboratively.
Key Concept
This question covers Demonstrate an understanding of project roles and responsibilities under Demonstrate an understanding of project roles and responsibilities (Project Management Fundamentals and Core Concepts).