CAPM Practice: Demonstrate an understanding of project roles and responsibilities

Question 88 of 94 in Demonstrate an understanding of project roles and responsibilities

Pick an answer below — you'll get the explanation instantly, no signup.

Matthias Fujimoto, a project manager at Aether Systems, is concerned that the project sponsor is not providing sufficient guidance on business priorities. What is the PRIMARY responsibility of the project sponsor that Matthias should emphasize?
Show answer & explanation

Correct answer: Providing funding authorization and ensuring the project aligns with business objectives

Explanation

The project sponsor's primary responsibility is to provide funding, authorize the project, and ensure alignment with organizational strategy and business objectives. The sponsor champions the project at the executive level.

**Why not A:** Documenting requirements and conducting stakeholder interviews are project manager or business analyst activities, not sponsor responsibilities. The sponsor provides strategic direction and resources, not detailed requirements documentation.

**Why not B:** Creating the detailed project schedule and assigning resources are project manager responsibilities during the planning phase. The sponsor operates at a higher level, providing funding authorization and business alignment, not detailed scheduling work.

**Why not C:** Managing day-to-day project activities and resolving team conflicts are core project manager responsibilities, not sponsor duties. The sponsor provides strategic oversight and organizational support while the project manager handles daily execution.

Key Concept

This question covers Demonstrate an understanding of project roles and responsibilities under Demonstrate an understanding of project roles and responsibilities (Project Management Fundamentals and Core Concepts).