CAPM Practice: Demonstrate an understanding of project roles and responsibilities
Question 40 of 94 in Demonstrate an understanding of project roles and responsibilities
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Facilitator
Explanation
Declan is acting as a facilitator by helping the team members work through their conflict, ensuring both voices are heard, and guiding them toward a resolution. Facilitators create an environment where the team can collaborate effectively and resolve issues.
**Why not A:** An initiator starts new initiatives or proposes new ideas. Declan is not proposing anything new; he is helping existing team members resolve a disagreement by guiding the discussion toward consensus, which is the facilitator role.
**Why not B:** A negotiator works to reach agreements on specific terms, resources, or contracts — typically between parties with competing interests. Declan is helping team members collaborate and find common ground through discussion, not negotiating terms or trade-offs between opposing positions.
**Why not C:** A working member performs the actual technical work on the project. Declan is not doing technical work here; he is guiding a process of conflict resolution and consensus-building, which is a facilitation activity rather than hands-on project work.
Key Concept
This question covers Demonstrate an understanding of project roles and responsibilities under Demonstrate an understanding of project roles and responsibilities (Project Management Fundamentals and Core Concepts).