CAPM Practice: Demonstrate an understanding of project roles and responsibilities
Question 84 of 94 in Demonstrate an understanding of project roles and responsibilities
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: The project sponsor, as they provide financial resources and authority
Explanation
The project sponsor is responsible for providing financial resources and has the authority to approve additional funding. While the project manager manages the budget day-to-day, major funding decisions require sponsor approval.
**Why not A:** While the project manager controls the day-to-day project budget, approving additional funding for scope changes exceeds their authority. Major financial decisions that increase the project's overall budget require sponsor authorization.
**Why not B:** The stakeholder who requested the change is not responsible for funding approval. Stakeholders can request changes, but the authority to approve additional funding rests with the project sponsor who controls the project's financial resources.
**Why not D:** The project team understands technical requirements but does not have authority over budget decisions. Approving additional funding is a strategic decision that falls within the project sponsor's authority, not the team's domain.
Key Concept
This question covers Demonstrate an understanding of project roles and responsibilities under Demonstrate an understanding of project roles and responsibilities (Project Management Fundamentals and Core Concepts).