CAPM Practice: Demonstrate an understanding of project roles and responsibilities
Question 69 of 94 in Demonstrate an understanding of project roles and responsibilities
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: The project manager executes the project while the sponsor provides strategic direction and resources
Explanation
The project manager is responsible for day-to-day execution of the project, while the sponsor provides high-level guidance, secures funding, removes organizational barriers, and makes key decisions that exceed the PM's authority. This represents the fundamental distinction between tactical execution and strategic oversight.
**Why not A:** The business case is typically created by the project sponsor, not the project manager. The project manager develops the project schedule, not the sponsor. This option reverses the key responsibilities of both roles.
**Why not B:** The project manager does not make all project decisions — some decisions, particularly those involving scope, budget, and strategic direction, require sponsor approval. The sponsor's role extends well beyond approving only the final deliverable.
**Why not C:** This option incorrectly assigns team management to the sponsor. The project manager manages the project team day-to-day, while the sponsor provides strategic direction and resources at the organizational level. The PM reports to stakeholders including the sponsor.
Key Concept
This question covers Demonstrate an understanding of project roles and responsibilities under Demonstrate an understanding of project roles and responsibilities (Project Management Fundamentals and Core Concepts).
All 1,500+ CAPM questions are free
Sign up to track your progress, see detailed analytics, and get personalized study recommendations.
Sign Up Free