CAPM Practice: Demonstrate an understanding of project roles and responsibilities
Question 50 of 94 in Demonstrate an understanding of project roles and responsibilities
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: 1. Project Sponsor → Removes organizational obstacles and provides executive-level support 2. Project Manager → Plans, executes, and monitors project activities on a day-to-day basis 3. Project Team Member → Provides subject matter expertise and completes assigned work packages 4. Functional Manager → Supplies resources from their department and manages performance reviews
Explanation
The project sponsor provides high-level support and removes barriers. The project manager handles daily project coordination and control. Team members execute the actual work. Functional managers provide resources from their organizational units and typically maintain administrative authority over team members.
**Why not B:** This option incorrectly assigns the project manager's planning duties to the sponsor, the team's execution role to the project manager, the functional manager's resource supply role to team members, and the sponsor's executive support responsibility to the functional manager. Every match is wrong.
**Why not C:** This option assigns resource supply to the sponsor and executive support to the functional manager. Although it correctly matches the project manager to planning and team members to execution, it incorrectly swaps the sponsor and functional manager roles.
**Why not D:** This option places execution responsibilities on the sponsor and planning on the functional manager, while assigning resource supply to the PM and executive support to team members. These mismatches contradict the established separation of strategic, tactical, and operational responsibilities.
Key Concept
This question covers Demonstrate an understanding of project roles and responsibilities under Demonstrate an understanding of project roles and responsibilities (Project Management Fundamentals and Core Concepts).