CAPM Practice: Demonstrate an understanding of project management planning
Question 2 of 100 in Demonstrate an understanding of project management planning
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: A milestone has zero duration while a task duration represents the time needed to complete work
Explanation
A milestone represents a significant point or event in the project and has zero duration—it marks achievement of a deliverable or phase. A task duration represents the actual time period required to complete work activities.
**Why not A:** Milestones do not require resources — they represent points in time with zero duration, not work activities. Tasks with durations consume resources to perform work, but milestones simply mark significant achievements or events.
**Why not B:** A milestone is not inherently part of the critical path, and task duration does not determine float. Float is determined by the relationship between an activity's earliest and latest possible start or finish dates in the schedule network, not by its duration alone.
**Why not D:** Neither milestones nor task durations are defined by specific units of measurement. Milestones have zero duration regardless of the time unit used, and task durations can be measured in any time unit (hours, days, weeks, or months) depending on the project context.
Key Concept
This question covers Demonstrate an understanding of project management planning under Demonstrate an understanding of project management planning (Project Management Fundamentals and Core Concepts).
All 1,500+ CAPM questions are free
Sign up to track your progress, see detailed analytics, and get personalized study recommendations.
Sign Up Free