CAPM Practice: Demonstrate an understanding of project management planning
Question 1 of 100 in Demonstrate an understanding of project management planning
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Risk management plan
Explanation
The risk management plan describes how risk management activities will be structured and performed, including the approach for handling identified threats and opportunities throughout the project.
**Why not A:** The quality management plan addresses quality standards, quality assurance, and quality control processes. It does not cover how to respond to identified threats and opportunities, which falls under risk management.
**Why not C:** The schedule management plan defines how the project schedule will be developed, monitored, and controlled. It does not describe approaches for handling threats and opportunities; that responsibility belongs to the risk management plan.
**Why not D:** The scope management plan defines how the project scope will be defined, validated, and controlled. It focuses on what is included and excluded from the project, not on managing risks or opportunities.
Key Concept
This question covers Demonstrate an understanding of project management planning under Demonstrate an understanding of project management planning (Project Management Fundamentals and Core Concepts).