CAPM Practice: Demonstrate an understanding of project management planning

Question 92 of 100 in Demonstrate an understanding of project management planning

Pick an answer below — you'll get the explanation instantly, no signup. A free account saves your progress.

Match each project management planning component on the left with its primary purpose on the right. Items: 1. Cost Management 2. Quality Management 3. Risk Register 4. Schedule Management Which option correctly matches each item to its description?
Show answer & explanation

Correct answer: 1. Cost Management → Determines how project budget will be estimated and controlled 2. Quality Management → Defines standards and how deliverables will meet requirements 3. Risk Register → Documents identified threats and opportunities with their responses 4. Schedule Management → Establishes how the project timeline will be developed and controlled

Explanation

Cost Management focuses on financial planning and control of the project budget. Quality Management ensures deliverables meet specified requirements and standards. The Risk Register is a living document that tracks identified risks (both threats and opportunities) along with their analysis and planned responses. Schedule Management establishes processes for developing, managing, and controlling the project timeline.

**Why not A:** This option swaps Cost Management and Schedule Management definitions. It assigns timeline development to Cost Management and budget control to Schedule Management — the exact opposite of their actual purposes.

**Why not B:** This option mismatches all four components. It assigns quality standards to Cost Management, risk documentation to Quality Management, timeline management to the Risk Register, and budget control to Schedule Management — none of the pairings are correct.

**Why not D:** This option assigns risk documentation to Cost Management, timeline development to Quality Management, budget control to the Risk Register, and quality standards to Schedule Management. Every pairing is incorrect, creating a complete mismatch of all four components.

Key Concept

This question covers Demonstrate an understanding of project management planning under Demonstrate an understanding of project management planning (Project Management Fundamentals and Core Concepts).