CAPM Practice: Demonstrate an understanding of project management planning
Question 99 of 100 in Demonstrate an understanding of project management planning
Pick an answer below — you'll get the explanation instantly, no signup. A free account saves your progress.
Show answer & explanation
Correct answer: Resource breakdown structure showing resource categories and quantities
Explanation
A resource breakdown structure (RBS) organizes and displays project resources by category and type, making it the appropriate tool to determine and document the number and types of resources needed for the project. It provides a hierarchical view of resources organized by resource category.
**Why not A:** An organizational chart shows reporting relationships and hierarchy but does not document the number and types of resources needed for a project. It shows who reports to whom, not what resources are required to complete the work.
**Why not B:** A responsibility assignment matrix (such as a RACI chart) shows who is responsible for what tasks but does not document the number and categories of resources needed. It focuses on role assignments for specific activities, not on overall resource quantity and type requirements.
**Why not C:** A stakeholder register lists all project stakeholders and their interests, influence, and engagement levels. It is not a tool for documenting resource categories and quantities needed for project work.
Key Concept
This question covers Demonstrate an understanding of project management planning under Demonstrate an understanding of project management planning (Project Management Fundamentals and Core Concepts).