Skip to content
CAPMEasy

CAPM Practice: Demonstrate an understanding of project management planning

Question 98 of 100 in Demonstrate an understanding of project management planning

Pick an answer below — you'll get the explanation instantly, no signup.

Ananya Choi is reviewing her project at Parallax Studios and notices that 'Complete design approval' is scheduled for June 15th with zero duration. What does this represent?
Show answer & explanation

Correct answer: A milestone marking a significant point in the project timeline

Explanation

A milestone is a significant point or event in a project that has zero duration. It marks the completion of a major deliverable or phase, such as obtaining design approval. Milestones are used to track progress and communicate key achievements to stakeholders.

**Why not A:** A zero-duration item in a schedule is not an error; it is a standard way to represent milestones. Milestones are intentionally set with zero duration to mark significant points in the timeline, so no correction is needed.

**Why not B:** Milestones do not require duration because they represent points in time, not work activities. Assigning a duration to a milestone would change its nature and misrepresent it in the schedule. Not all schedule items require work duration.

**Why not C:** A summary task rolls up the durations of its subordinate activities and typically shows a non-zero duration spanning the work beneath it. A zero-duration item specifically indicates a milestone, not a summary task.

Key Concept

This question covers Demonstrate an understanding of project management planning under Demonstrate an understanding of project management planning (Project Management Fundamentals and Core Concepts).

Share:

All 1,500+ CAPM questions are free

Sign up to track your progress, see detailed analytics, and get personalized study recommendations.

Sign Up Free