CAPM Practice: Demonstrate an understanding of project management planning
Question 66 of 100 in Demonstrate an understanding of project management planning
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: A milestone represents a significant point or event in the project with zero duration, while a task duration represents the time required to complete a specific activity
Explanation
A milestone marks a significant point or event in the project schedule and has zero duration—it represents a moment in time. A task duration represents the amount of time needed to complete a specific work activity and has a measurable length (hours, days, weeks, etc.).
**Why not A:** Milestones are used in both agile and predictive projects. They are not methodology-specific. In any approach, milestones mark key achievements or decision points, while task durations measure the time to complete work.
**Why not C:** Milestones can occur at any point in the project, not just at the end of phases. They mark significant events such as approvals, deliverable completions, or key decision points throughout the entire project lifecycle.
**Why not D:** A milestone has zero duration, not one day. It represents a point in time, not a period. Task durations can range from hours to weeks, but the key distinction is that milestones mark moments while tasks span time.
Key Concept
This question covers Demonstrate an understanding of project management planning under Demonstrate an understanding of project management planning (Project Management Fundamentals and Core Concepts).
All 1,500+ CAPM questions are free
Sign up to track your progress, see detailed analytics, and get personalized study recommendations.
Sign Up Free