CAPM Practice: Demonstrate an understanding of project management planning
Question 14 of 100 in Demonstrate an understanding of project management planning
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: To ensure the project is completed within the approved budget
Explanation
Cost planning establishes the budget and cost baseline, and provides the framework for monitoring and controlling costs so the project stays within the approved budget. It ensures financial resources are allocated appropriately throughout the project lifecycle.
**Why not A:** Calculating team member salaries and benefits is an HR and organizational function, not the primary purpose of cost planning. While labor costs are part of the project budget, cost planning encompasses all project expenses and focuses on budget management.
**Why not B:** Cost planning does not aim to eliminate all non-essential expenses. Its purpose is to establish the budget baseline and control costs to stay within the approved budget, not to minimize spending at all costs.
**Why not C:** Determining the selling price of the final product is a business and marketing function outside the scope of project cost management. Cost planning focuses on managing the project's internal costs, not the product's market price.
Key Concept
This question covers Demonstrate an understanding of project management planning under Demonstrate an understanding of project management planning (Project Management Fundamentals and Core Concepts).