CAPM Practice: Demonstrate an understanding of project management planning

Question 25 of 100 in Demonstrate an understanding of project management planning

Pick an answer below — you'll get the explanation instantly, no signup.

Nia Adebayo is reviewing her project management plan. Which component would contain information about how the project team will be structured and when resources will be needed?
Show answer & explanation

Correct answer: Resource management plan

Explanation

The resource management plan is a component of the project management plan that describes how project resources will be acquired, allocated, monitored, and controlled. It includes team structure, resource requirements, and timing.

**Why not A:** The product management plan describes the product's features, specifications, and lifecycle — not how the team will be structured or when resources are needed. Team structure and resource timing are project execution concerns addressed in the resource management plan.

**Why not C:** The communications management plan defines how information will be distributed to stakeholders, including methods, frequency, and channels. It does not address team structure or resource scheduling, which fall under resource management planning.

**Why not D:** The quality management plan describes how quality standards will be met, including inspection criteria and quality assurance activities. It does not address project team structure or the timing of resource needs.

Key Concept

This question covers Demonstrate an understanding of project management planning under Demonstrate an understanding of project management planning (Project Management Fundamentals and Core Concepts).

Share: