CAPM Practice: Demonstrate an understanding of product roadmaps
Question 51 of 67 in Demonstrate an understanding of product roadmaps
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: The roadmap provides strategic context — near-term roadmap themes guide which backlog items should be prioritized for the upcoming Sprint
Explanation
During Sprint Planning, the team selects items that advance near-term roadmap themes and Sprint Goals. The roadmap ensures that Sprint commitments are strategically aligned rather than opportunistic — connecting daily work to the product's strategic direction.
**Why not B:** Sprint Planning does not create the product roadmap. The roadmap is a strategic artifact maintained by the product owner or product manager at a higher level than individual sprints. Sprint Planning selects work from an already-prioritized backlog; it does not aggregate sprint content upward into a release plan.
**Why not C:** The product roadmap is not presented for stakeholder approval during Sprint Planning. Sprint Planning is a team-internal event focused on selecting and planning work for the upcoming sprint. Roadmap reviews and stakeholder approvals happen in separate forums such as roadmap reviews or portfolio meetings.
**Why not D:** Ignoring the roadmap during Sprint Planning would disconnect sprint-level execution from strategic direction. The roadmap provides essential context about near-term priorities and themes, helping the team understand why certain backlog items are being prioritized and ensuring sprint work aligns with broader product goals.
Key Concept
This question covers Demonstrate an understanding of product roadmaps under Demonstrate an understanding of product roadmaps (Business Analysis Frameworks).