CAPM Practice: Demonstrate an understanding of common problem-solving tools and techniques

Question 19 of 105 in Demonstrate an understanding of common problem-solving tools and techniques

Pick an answer below — you'll get the explanation instantly, no signup.

Ren Cardenas is planning various meetings for a project at Crosswind Aviation. Match each meeting purpose on the left with the most appropriate problem-solving tool or technique on the right. Items: 1. Gather customer feedback on a new product feature 2. Coordinate daily team activities and identify blockers 3. Generate multiple creative solutions to a technical challenge 4. Review what worked well and what needs improvement after a sprint Which option correctly matches each item to its description?
Show answer & explanation

Correct answer: 1. Gather customer feedback on a new product feature → Focus group 2. Coordinate daily team activities and identify blockers → Standup meeting 3. Generate multiple creative solutions to a technical challenge → Brainstorming session 4. Review what worked well and what needs improvement after a sprint → Retrospective meeting

Explanation

Focus groups gather qualitative feedback from target audiences like customers. Standup meetings provide daily coordination and blocker identification. Brainstorming sessions generate creative ideas and solutions. Retrospective meetings reflect on past work to identify improvements.

**Why not A:** This option mismatches all four items. Customer feedback should use a focus group, not brainstorming. Daily coordination should use a standup, not a retrospective. Creative solutions should use brainstorming, not a focus group. Sprint reflection should use a retrospective, not a standup.

**Why not C:** This option assigns a standup meeting for customer feedback, brainstorming for daily coordination, a retrospective for creative solutions, and a focus group for sprint reflection. All four pairings are incorrect, with each technique matched to the wrong meeting purpose.

**Why not D:** This option correctly matches daily coordination to a standup and creative solutions to brainstorming, but incorrectly assigns a retrospective for customer feedback and a focus group for sprint reflection. Customer feedback requires a focus group, and sprint reflection requires a retrospective.

Key Concept

This question covers Demonstrate an understanding of common problem-solving tools and techniques under Demonstrate an understanding of common problem-solving tools and techniques (Project Management Fundamentals and Core Concepts).