CAPM Practice: Demonstrate an understanding of common problem-solving tools and techniques

Question 43 of 105 in Demonstrate an understanding of common problem-solving tools and techniques

Pick an answer below — you'll get the explanation instantly, no signup.

The Nominal Group Technique (NGT) differs from brainstorming primarily because it:
Show answer & explanation

Correct answer: Allows silent idea generation followed by structured voting to prioritize ideas

Explanation

The Nominal Group Technique structures group decision-making by having participants silently generate ideas independently, then share and discuss them, and finally vote to prioritize. This prevents dominant personalities from controlling the discussion and ensures all voices are heard.

**Why not A:** Using a facilitator to collect ideas anonymously from experts describes the Delphi technique, not the Nominal Group Technique. NGT involves in-person participants who generate ideas silently and then discuss and vote, rather than anonymous collection through a facilitator.

**Why not B:** The Nominal Group Technique does not require all participants to be domain experts. It is designed to be inclusive and works with participants of varying expertise levels, using structured voting to give equal weight to each person's input.

**Why not C:** NGT is conducted synchronously with all participants present in the same session. Asynchronous interaction without real-time participation is more characteristic of the Delphi technique, where rounds of feedback are collected over time.

Key Concept

This question covers Demonstrate an understanding of common problem-solving tools and techniques under Demonstrate an understanding of common problem-solving tools and techniques (Project Management Fundamentals and Core Concepts).