CAPM Practice: Demonstrate an understanding of common problem-solving tools and techniques
Question 36 of 105 in Demonstrate an understanding of common problem-solving tools and techniques
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Identifying which few causes are responsible for the majority of problems
Explanation
A Pareto chart applies the 80/20 rule, showing that roughly 80% of problems are caused by 20% of causes. By ranking causes in descending order of frequency, it helps project managers focus improvement efforts on the most impactful issues first.
**Why not A:** Showing the trend of defects over time is the purpose of a control chart or run chart, not a Pareto chart. A Pareto chart ranks categories by frequency in a single period, not over time.
**Why not C:** Mapping the flow of a process from start to finish is the purpose of a flowchart or process map. A Pareto chart displays ranked categorical data, not process sequences.
**Why not D:** Comparing planned versus actual project performance is the purpose of variance analysis or earned value management tools. A Pareto chart focuses on identifying the most significant causes of problems, not tracking performance against a baseline.
Key Concept
This question covers Demonstrate an understanding of common problem-solving tools and techniques under Demonstrate an understanding of common problem-solving tools and techniques (Project Management Fundamentals and Core Concepts).