CAPM Practice: Demonstrate an understanding of common problem-solving tools and techniques
Question 72 of 105 in Demonstrate an understanding of common problem-solving tools and techniques
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Divergent thinking followed by convergent thinking
Explanation
Effective problem-solving involves divergent thinking (generating as many ideas as possible without judgment) followed by convergent thinking (evaluating and narrowing options to select the best solution). This two-phase approach is the foundation of brainstorming and many other creative problem-solving techniques.
**Why not A:** Risk identification and analysis are related to managing project uncertainties, not to solving customer complaints through creative idea generation. The scenario describes a structured approach to generating and evaluating solutions, not assessing risks.
**Why not B:** Lessons learned and process improvement occur after project work is complete or during retrospectives. The scenario describes an active problem-solving session where the team generates ideas before evaluating them, which is a creative thinking process.
**Why not D:** Issue logging and resolution is an administrative tracking process. The scenario specifically describes a structured technique where ideas are first generated without criticism, then evaluated, which is the hallmark of divergent-then-convergent thinking.
Key Concept
This question covers Demonstrate an understanding of common problem-solving tools and techniques under Demonstrate an understanding of common problem-solving tools and techniques (Project Management Fundamentals and Core Concepts).