CAPMMedium
CAPM Practice: Demonstrate an understanding of a project management plan schedule
A project network diagram shows five paths through the project. Path durations are: 45, 38, 51, 47, and 39 days. What is the project's critical path duration and when can the project be completed earliest?
Key Concept
This question covers Demonstrate an understanding of a project management plan schedule under Demonstrate an understanding of a project management plan schedule (Predictive, Plan-Based Methodologies).
All 1,500+ CAPM questions are free
Sign up to track your progress, see detailed analytics, and get personalized study recommendations.
Sign Up Free