Skip to content
CAPMMedium

CAPM Practice: Demonstrate an understanding of a project management plan schedule

A project network diagram shows five paths through the project. Path durations are: 45, 38, 51, 47, and 39 days. What is the project's critical path duration and when can the project be completed earliest?

Key Concept

This question covers Demonstrate an understanding of a project management plan schedule under Demonstrate an understanding of a project management plan schedule (Predictive, Plan-Based Methodologies).

All 1,500+ CAPM questions are free

Sign up to track your progress, see detailed analytics, and get personalized study recommendations.

Sign Up Free