A project manager reviews project dependencies and identifies that Activity F cannot start until both Activity D and Activity E are complete. This creates what type of network logic?

Key Concept

This question covers Demonstrate an understanding of a project management plan schedule under Demonstrate an understanding of a project management plan schedule (Predictive, Plan-Based Methodologies).