Skip to content
CAPMMedium

CAPM Practice: Demonstrate an understanding of a project management plan schedule

A project manager discovers that the cost to crash Activity X by 3 days is $15,000 ($5,000/day), and the cost to crash Activity Y by 2 days is $12,000 ($6,000/day). Both are on the critical path. To save 2 days of project time at the LOWEST cost, which activity should she crash?

Key Concept

This question covers Demonstrate an understanding of a project management plan schedule under Demonstrate an understanding of a project management plan schedule (Predictive, Plan-Based Methodologies).

All 1,500+ CAPM questions are free

Sign up to track your progress, see detailed analytics, and get personalized study recommendations.

Sign Up Free