CAPM Practice: Demonstrate an understanding of a project management plan schedule

Question 46 of 85 in Demonstrate an understanding of a project management plan schedule

Pick an answer below — you'll get the explanation instantly, no signup.

The project schedule management plan defines:
Show answer & explanation

Correct answer: How the project schedule will be developed, monitored, and controlled

Explanation

The schedule management plan is a subsidiary plan within the project management plan that defines HOW the schedule will be managed: the scheduling methodology (e.g., CPM), tools, update frequency, performance thresholds that trigger action, change control procedures for schedule changes, and reporting formats. It doesn't contain the actual schedule dates — that's the project schedule itself.

**Why not A:** The list of approved team members is part of the resource management plan or project team assignments, not the schedule management plan. The schedule management plan defines how scheduling will be done, not who will do the work.

**Why not B:** Cost information for scheduled activities belongs in the cost management plan and cost baseline. The schedule management plan addresses timing and scheduling methodology, not cost estimation or budgeting.

**Why not C:** Specific start and finish dates are contained in the project schedule itself, which is an output of the scheduling process. The schedule management plan defines the approach and methodology for creating the schedule, not the actual dates.

Key Concept

This question covers Demonstrate an understanding of a project management plan schedule under Demonstrate an understanding of a project management plan schedule (Predictive, Plan-Based Methodologies).