CAPM Practice: Demonstrate an understanding of a project management plan schedule
Question 33 of 85 in Demonstrate an understanding of a project management plan schedule
Show answer & explanation
Correct answer: A grouping of related activities that shows their combined duration and dates as a summary bar
Explanation
A summary activity (hammock or summary bar in Gantt charts) spans multiple subordinate activities, showing their collective start and end dates as a single bar. In WBS-based schedules, they represent work packages or phases, with the summary bar spanning from the earliest start to the latest finish of all activities within the group.
**Why not B:** An activity that must be completed before the project can begin describes a predecessor or prerequisite, not a summary activity. Summary activities aggregate groups of subordinate activities rather than serving as preconditions.
**Why not C:** A critical path activity with the longest duration describes a specific scheduling characteristic, not the concept of a summary activity. Summary activities span their child activities regardless of whether those activities are on the critical path.
**Why not D:** An activity performed by a resource working across multiple projects describes a shared resource situation, not a summary activity. Summary activities are a scheduling construct that groups related work, unrelated to how resources are allocated.
Key Concept
This question covers Demonstrate an understanding of a project management plan schedule under Demonstrate an understanding of a project management plan schedule (Predictive, Plan-Based Methodologies).