Skip to content
CAPMHard

CAPM Practice: Demonstrate an understanding of a project management plan schedule

Question 34 of 85 in Demonstrate an understanding of a project management plan schedule

Pick an answer below — you'll get the explanation instantly, no signup.

A project manager is developing a schedule for a complex project with 250 activities. She discovers that 45 activities have the same late finish date as the project end date and zero float. This means:
Show answer & explanation

Correct answer: Multiple parallel critical paths converge at the project end, so a slip in any of these 45 activities delays the project, creating a significant risk that the project will be late

Explanation

Multiple activities with zero float (especially when they converge at the project end) indicate multiple parallel critical paths. This is actually a high-risk scheduling situation because if ANY of the 45 activities slips, the project end date is threatened. A project with multiple parallel paths all ending at the same date with zero float is more schedule-fragile than one with a single critical path.

**Why not A:** While all 45 activities do have zero float and are technically on the critical path, stating they "must all be monitored equally" misses the key insight. The real significance is the convergence risk — having so many parallel paths with zero float creates extreme schedule fragility requiring risk-aware management strategies beyond just equal monitoring.

**Why not B:** Having 250 activities with 45 on the critical path is not a sign of overplanning. Complex projects routinely have many activities, and the number of critical activities depends on the network structure. The activity count itself does not indicate a planning error.

**Why not C:** Projects can have multiple critical paths simultaneously. A single critical path is common but not required. When multiple parallel paths all have zero float, each represents a critical path. This is a valid (though risky) schedule network structure, not an error.

Key Concept

This question covers Demonstrate an understanding of a project management plan schedule under Demonstrate an understanding of a project management plan schedule (Predictive, Plan-Based Methodologies).

Share:

All 1,500+ CAPM questions are free

Sign up to track your progress, see detailed analytics, and get personalized study recommendations.

Sign Up Free