CAPM Practice: Demonstrate an understanding of a project management plan schedule
Question 34 of 85 in Demonstrate an understanding of a project management plan schedule
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: There are 45 near-critical paths that all become critical simultaneously at the end, creating a significant risk that the project will be late
Explanation
Multiple activities with zero float (especially when they converge at the project end) indicate near-critical paths or parallel critical paths. This is actually a high-risk scheduling situation because if ANY of the 45 activities slips, the project end date is threatened. A project with multiple parallel paths all ending at the same date with zero float is more schedule-fragile than one with a single critical path.
**Why not A:** While all 45 activities do have zero float and are technically on the critical path, stating they "must all be monitored equally" misses the key insight. The real significance is the convergence risk — having so many parallel paths with zero float creates extreme schedule fragility requiring risk-aware management strategies beyond just equal monitoring.
**Why not B:** Having 250 activities with 45 on the critical path is not a sign of overplanning. Complex projects routinely have many activities, and the number of critical activities depends on the network structure. The activity count itself does not indicate a planning error.
**Why not C:** Projects can have multiple critical paths simultaneously. A single critical path is common but not required. When multiple parallel paths all have zero float, each represents a critical path. This is a valid (though risky) schedule network structure, not an error.
Key Concept
This question covers Demonstrate an understanding of a project management plan schedule under Demonstrate an understanding of a project management plan schedule (Predictive, Plan-Based Methodologies).
All 1,500+ CAPM questions are free
Sign up to track your progress, see detailed analytics, and get personalized study recommendations.
Sign Up Free