CAPM Practice: Demonstrate an understanding of a project management plan schedule
Question 81 of 85 in Demonstrate an understanding of a project management plan schedule
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Planning
Explanation
The Schedule Management Plan is created during the Planning process group, specifically through the 'Plan Schedule Management' process. It establishes how the schedule will be developed, monitored, and controlled throughout the project. It is one of many subsidiary management plans created during project planning.
**Why not A:** The Initiating process group produces the project charter and identifies stakeholders. The Schedule Management Plan requires inputs from initiation (such as the charter) and is developed during the Planning process group, not during initiation.
**Why not C:** The Closing process group focuses on finalizing all project work, obtaining formal acceptance, and documenting lessons learned. No management plans are created during closing — they are created during planning and used throughout execution.
**Why not D:** The Executing process group carries out the work defined in the project management plan. Management plans, including the Schedule Management Plan, are created during planning to guide execution. They are followed during execution, not created during it.
Key Concept
This question covers Demonstrate an understanding of a project management plan schedule under Demonstrate an understanding of a project management plan schedule (Predictive, Plan-Based Methodologies).
All 1,500+ CAPM questions are free
Sign up to track your progress, see detailed analytics, and get personalized study recommendations.