CAPM Practice: Demonstrate an understanding of a project management plan schedule
Question 2 of 85 in Demonstrate an understanding of a project management plan schedule
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: The longest path through the network, which determines the shortest possible project duration
Explanation
The critical path is the longest sequence of dependent activities through the project network. It determines the earliest possible project completion date — any delay on the critical path directly delays the project. Activities on the critical path have zero float (slack) and receive the highest schedule monitoring priority.
**Why not A:** The critical path is not determined by the number of activities on a path. A path with fewer activities could have longer total duration than a path with many short activities. The critical path is the longest path in terms of total duration, not activity count.
**Why not B:** The critical path has nothing to do with the cost of activities. It is determined solely by activity durations and dependencies. The most expensive activities may or may not be on the critical path, as cost and duration are independent schedule characteristics.
**Why not D:** While the project manager should monitor the critical path closely, this describes a management practice, not the definition of the critical path. The critical path is defined objectively by the schedule network analysis as the longest duration path, regardless of monitoring attention.
Key Concept
This question covers Demonstrate an understanding of a project management plan schedule under Demonstrate an understanding of a project management plan schedule (Predictive, Plan-Based Methodologies).