CAPM Practice: Demonstrate an understanding of a project management plan schedule
Question 23 of 85 in Demonstrate an understanding of a project management plan schedule
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Evaluate crashing and fast tracking options on remaining critical path activities to recover the lost time
Explanation
With a fixed deadline and activities behind schedule, the project manager must evaluate schedule compression options. Crashing (adding resources) and fast tracking (parallelizing activities) are the primary tools. The PM should analyze which remaining activities offer the best opportunity for recovery with acceptable risk and cost, then implement the most viable combination.
**Why not A:** Accepting the delay and notifying stakeholders without attempting recovery is premature. A project manager should first evaluate whether schedule compression techniques can recover the lost time before concluding that the deadline cannot be met.
**Why not B:** Asking the sponsor to extend the deadline by 2 weeks surrenders without exploring recovery options. The project manager should first analyze crashing and fast tracking possibilities on the remaining critical path activities to determine if the schedule can be recovered within the existing constraints.
**Why not D:** Reducing quality requirements to speed up work is generally unacceptable and should be a last resort. Quality standards exist for a reason, and compromising them could result in deliverables that do not meet acceptance criteria or stakeholder expectations. Schedule compression should be evaluated first.
Key Concept
This question covers Demonstrate an understanding of a project management plan schedule under Demonstrate an understanding of a project management plan schedule (Predictive, Plan-Based Methodologies).