Simulation
Simulation is a data analysis technique that uses mathematical models to evaluate the probability of various project outcomes by running multiple iterations with variable inputs, most commonly through Monte Carlo analysis.
Know it well enough for the exam? Questions on Simulation are scenario-based, not definitional.
Practice it freeExplanation
Simulation in project management typically refers to Monte Carlo simulation, a technique that uses probability distributions for activity durations, costs, or other variables to calculate the likelihood of different project outcomes. The simulation runs thousands of iterations, each time randomly sampling values from the defined distributions, to produce a probability distribution of possible results.
Monte Carlo simulation is most commonly applied to schedule risk analysis and cost risk analysis. For schedule analysis, it produces a probability curve showing the likelihood of completing the project by various dates. For cost analysis, it shows the probability of completing within various budget amounts. This information helps project managers set realistic targets and determine appropriate contingency reserves.
Simulation requires specialized software tools and well-defined probability distributions for input variables. While more complex than deterministic techniques, it provides significantly more insight into project risk by quantifying the range of possible outcomes rather than relying on a single-point estimate.
Key Points
- •Monte Carlo is the most common simulation technique in project management
- •Runs thousands of iterations with randomly sampled input variables
- •Produces probability distributions of possible project outcomes
- •Used primarily for schedule risk analysis and cost risk analysis
Exam Tip
Monte Carlo simulation produces a probability distribution, not a single answer. It tells you the likelihood of meeting a target date or budget. Know that it requires specialized software.
Frequently Asked Questions
Related Topics
What-If Scenario Analysis
What-if scenario analysis is a data analysis technique that evaluates how different scenarios or conditions would affect project outcomes, enabling proactive planning for various possibilities.
Agile Estimation Techniques
Agile estimation techniques are lightweight methods used by agile teams to estimate the size, effort, or complexity of work items, including story points, planning poker, T-shirt sizing, and relative estimation.
Data Analysis Techniques
Data analysis techniques are methods used to process, evaluate, and draw conclusions from project data to support informed decision-making and performance assessment.
Most-studied PMP concepts
High-yield topics our learners drill most before exam day.
Matrix Diagrams
Matrix diagrams are a data representation technique that uses a grid format to show relationships between two or more groups of factors, commonly used for responsibility assignments and prioritization.
Burndown Chart
A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.
Burn-Up Chart
A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.
Resource Leveling
Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.
Deliverables
A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.
Power Interest Grid (Power/Influence Grid)
The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.
Critical Path Method (CPM)
The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.
Weighted Shortest Job First (WSJF)
Weighted Shortest Job First (WSJF) is a prioritization model, popularized by SAFe, that ranks work by cost of delay divided by job duration (usually estimated as job size), so the items that lose the most value per unit of time spent waiting are done first.
Risk Register
The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.
Part of
Tools & Techniques
Practice Simulation
Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.