Skip to content
PMPCAPM

Kill Points

Kill points are predetermined decision points in a project life cycle where stakeholders have the explicit option to terminate the project based on performance, viability, or strategic relevance.

Share:

Know it well enough for the exam? Questions on Kill Points are scenario-based, not definitional.

Practice it free

Explanation

Kill points are closely related to phase gates but carry a specific emphasis on the termination option. While every phase gate technically includes the possibility of stopping the project, a kill point makes this option explicit and prominent. The purpose is to prevent the sunk-cost fallacy, where organizations continue investing in failing projects simply because they have already spent significant resources.

At a kill point, the review authority evaluates whether the project still makes business sense. Has the market changed? Have costs escalated beyond acceptable limits? Has a competitor launched a similar product? Are the technical challenges insurmountable? If the answer to any of these questions undermines the project's viability, the project should be terminated, and remaining resources should be redirected to higher-value work.

Establishing kill points at the beginning of a project is a best practice in project governance. It normalizes the decision to stop a project, removing the stigma that often prevents organizations from making rational termination decisions.

Key Points

  • •Explicit decision points where project termination is a primary option
  • •Designed to prevent the sunk-cost fallacy
  • •Evaluate continued business viability and strategic relevance
  • •Should be defined during project planning as part of governance

Exam Tip

Kill points and phase gates are related but not identical. If the exam question emphasizes the decision to terminate a project, the answer is a kill point. If it emphasizes a general review and go/no-go decision, it is a phase gate.

Frequently Asked Questions

Related Topics

High-yield topics our learners drill most before exam day.

Project Governance

Project governance is the framework of authority, accountability, policies, and decision-making processes that guide a project from initiation through closure, ensuring alignment with organizational strategy and stakeholder expectations.

Burndown Chart

A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.

Burn-Up Chart

A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.

Resource Leveling

Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.

Deliverables

A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.

Power Interest Grid (Power/Influence Grid)

The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.

Critical Path Method (CPM)

The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.

Weighted Shortest Job First (WSJF)

Weighted Shortest Job First (WSJF) is a prioritization model, popularized by SAFe, that ranks work by cost of delay divided by job duration (usually estimated as job size), so the items that lose the most value per unit of time spent waiting are done first.

Risk Register

The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.

Part of

Organizational Structures & Governance

Study full domain →

Practice Kill Points

Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.