How to run a PMP study cohort at work

The main thing a study cohort gives people that solo study does not is a schedule and a date. This is a simple eight-week structure that holds up, written for the 2026 exam outline, plus the four habits that keep cohorts from stalling.

The 8-week plan

Before week 1

Set the date and the rules

Pick a target window for everyone to sit the exam, about two weeks after the cohort ends. Make sure each person has their 35 contact hours done or scheduled, and has started the PMI application.

Weeks 1–2

Baseline

Everyone takes a diagnostic across all three domains. You learn who is close and who is starting cold, and each person learns which domain to start with. Do not compare scores in public.

Weeks 3–6

Domain blocks, weighted like the exam

Study in proportion to the 2026 outline: Process 41%, People 33%, Business Environment 26%. Roughly a week and a half on Process, a week and a bit on People, and a full week on Business Environment, which older material covers least.

Week 7

One full mock exam

Each person sits a full 180-question timed exam: 230 minutes, with the two optional breaks. Most people have never concentrated on a test that long, and the mock is where they find out.

Week 8

Review misses, then book

Spend the week only on questions people got wrong and why the wrong answer looked right. Anyone scoring consistently well across all three domains books the exam that week, while it is fresh.

Four habits that keep a cohort moving

A shared booking target, set in week 1

The single biggest cause of stalled cohorts is no exam date. A shared window turns "studying for the PMP" into a deadline.

A 30-minute weekly check-in about misses

People bring the questions they got wrong, not the ones they got right. Explaining why a tempting answer is wrong is where most of the learning happens, and it is the part self-study skips.

Protected study time

Two or three hours a week on the calendar, approved by each person's manager. Study that only happens after hours is the first thing cut when a project gets busy.

A plan for people who fall behind

Someone will. Let them move to the next cohort instead of dropping out, and keep their seat and progress.

Practice seats for your cohort

GanttGrind gives each person lifetime PMP and CAPM practice: the baseline diagnostic, domain drills weighted to the 2026 outline, full timed mock exams and readiness by domain. Seats start at $19 per person, on one invoice.

See team seat pricing

Questions

How many people should be in a PMP study cohort?

Four to twelve works well. Fewer than four and the weekly check-in loses energy; more than twelve and the discussion of missed questions gets too long. Split bigger groups into two cohorts with the same schedule.

Is eight weeks enough to pass the PMP?

For people with the required experience who have finished their 35 contact hours, eight weeks of steady study is a common timeline. The week 7 mock exam is the check: people who are not consistently passing domain practice yet should take a few more weeks before booking.

Can CAPM candidates join the same cohort?

Yes. The CAPM covers similar ground at an earlier level, and junior staff benefit from hearing how experienced PMs reason through scenario questions. Give them CAPM practice and the same weekly check-in.

What does a cohort need besides a course?

A question bank with full-length timed mocks and a way to see each person's weak domains. GanttGrind team seats include both, with one code per employee.