PMP Practice: Manage scope changes
Question 4 of 5 in Plan and Manage Scope
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Facilitate a joint session with both teams and the product owner to assess the scope change impact, update the scope baseline through formal change control for the infrastructure workstream, and collaborate on integrating the API work into upcoming sprint planning
Explanation
In a hybrid project with both predictive and adaptive components, scope management must honor the different approaches while maintaining overall project coherence. The infrastructure scope baseline requires formal change control, while the agile UI work allows for evolving requirements. The correct recovery action is to bring all parties together to assess the full impact, follow proper change control for the predictive workstream, and collaboratively integrate the work. This addresses the root cause—misalignment between the two workstreams—and establishes a path forward that respects both methodologies. The scenario includes a closing fact: the development team has already started work, making immediate collaborative recovery essential rather than deferral or escalation.
**Why not A:** Asking the product owner to deprioritize UI features does not resolve the governance issue. The infrastructure scope baseline was changed without formal change control, and shifting UI priorities does not address the fact that backend APIs were added outside the approved scope or reconcile the predictive workstream's disrupted baseline.
**Why not B:** Pausing implementation and deferring APIs to a future phase ignores the fact that the development team has already started work. This creates waste and does not address the integration need between the two workstreams. Additionally, the product owner identified these features as essential for the minimum viable product.
**Why not C:** Escalating to the sponsor for approval of the scope change and delay bypasses the collaborative recovery that both teams need. The PM should first facilitate a joint assessment to understand options and impacts before escalating, and the sponsor will need an informed recommendation rather than just a request for delay approval.