PMP Practice: Estimate project tasks (milestones, dependencies, story points)
Question 1 of 5 in Plan and Manage Schedule
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Transition to iterative development with fixed-length sprints, using velocity tracking and a prioritized backlog to measure progress toward business value
Explanation
This scenario presents characteristics that strongly favor an agile approach: rapidly changing market conditions, uncertain requirements revealed through prototype feedback, a need for frequent stakeholder visibility to make funding decisions, and a learning curve with new technology. The sponsor's need to see working features monthly to adjust market positioning indicates that delivering incremental value is more important than following a predetermined plan. Using iterative development with fixed-length sprints allows the team to respond to market changes, incorporate user feedback quickly, adapt to the learning curve with AI frameworks, and provide the monthly working features the sponsor needs for decision-making. Velocity tracking provides a reliable measure of progress based on delivered functionality rather than plan compliance, which is appropriate when requirements are evolving. The combination of frequent delivery, stakeholder engagement, and adaptability addresses all the scenario's challenges.
**Why not A:** Maintaining the 18-month Gantt chart with monthly variance reports preserves a planning artifact that no longer fits the project context. Market conditions are changing rapidly, requirements have diverged from assumptions, and the sponsor now wants working features monthly. Reporting variance against an outdated plan provides little value.
**Why not B:** Creating a hybrid schedule with predictive AI framework work and agile UI sprints splits the project in a way the scenario does not support. Both the AI work and the UI features face uncertainty (the team has limited AI experience and user preferences differ from assumptions), and the sponsor wants to see integrated working features monthly across all components.
**Why not D:** Rolling wave planning with detailed near-term schedules and high-level milestones is better suited for projects where requirements are reasonably stable in the near term. With competitors launching features monthly and the sponsor wanting to make funding decisions based on working software, iterative delivery with velocity tracking provides more relevant progress measurement than even a rolling wave Gantt chart.
Key Concept
This question covers Estimate project tasks (milestones, dependencies, story points) under Plan and Manage Schedule (Process).