PMP Practice: Determine necessary approach and action to address compliance needs
Question 6 of 6 in Plan and Manage Project Compliance
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Use a predictive approach with phase gates aligned to regulatory milestones and formal documentation requirements
Explanation
This project operates in a highly regulated environment with fixed regulatory requirements, mandatory phase gates, and predetermined inspection points. The FDA compliance framework, construction permits requiring pre-approved designs, and GMP validation protocols demand a predictive approach with detailed upfront planning and sequential phase progression. Regulatory compliance cannot be addressed iteratively when government agencies require approved documentation before proceeding to subsequent phases. The predictive approach provides the necessary structure for managing mandatory compliance checkpoints, formal validation processes, and inspection schedules that cannot be adapted or changed mid-project. While team engagement is valuable, the regulatory constraints make this unsuitable for agile or hybrid approaches.
**Why not A:** Beginning with agile sprints and transitioning to predictive after design validation contradicts the regulatory reality of this project. The FDA has already scheduled compliance audits tied to specific completion gates, and construction permits require approved architectural drawings before foundation work begins. Starting iteratively would immediately conflict with the permit requirements that exist before a single sprint could be completed.
**Why not B:** Adopting agile sprints for the entire project would make regulatory compliance impossible. FDA GMP validation protocols and government inspections at specific construction phases require sequential, documented progression through predefined milestones. Two-week sprints cannot produce the complete documentation packages required at each compliance gate or align with the external inspection schedule set by regulators.
**Why not C:** A hybrid approach using agile for construction activities fundamentally misapplies where each methodology should go. Physical construction of a sterile manufacturing facility follows fixed sequences determined by engineering, permitting, and physical reality—it cannot be iterated. Regulatory documentation, while important, is the output of a defined process and does not drive the need for predictive scheduling; the construction sequence itself does.
Key Concept
This question covers Determine necessary approach and action to address compliance needs under Plan and Manage Project Compliance (Business Environment).
This is 1 of 100 free PMP questions
Unlock 6,300+ PMP practice questions with detailed explanations, progress tracking, and exam readiness prediction.
Unlock All Questions