PMP Practice: Confirm Compliance Requirements

Question 1 of 6 in Plan and Manage Project Compliance

Pick an answer below — you'll get the explanation instantly, no signup.

Lucía Delgado-Vega is managing a solar farm installation project for Rio Fontaine-Baptiste Collective across three western states. The project operates under a hybrid approach with predictive phases for regulatory approval and agile sprints for installation optimization. The organization must maintain continuous compliance with federal Environmental Protection Agency (EPA) emission reduction standards, which require documented proof that at least 85% of project activities meet sustainability criteria. Lucía is preparing the quarterly compliance report and needs to calculate the current compliance rate. The project has completed 240 work packages to date. Of these, 198 work packages have full sustainability documentation, 18 work packages are pending final environmental impact assessments that will likely be approved within two weeks, and 24 work packages involve legacy equipment that cannot meet current sustainability standards but are grandfathered under previous regulations. The compliance office has clarified that only work packages with completed documentation count toward the 85% threshold—pending assessments and grandfathered exceptions do not qualify as compliant for reporting purposes. What is the project's current compliance rate?
Show answer & explanation

Correct answer: 82.5%

Explanation

The compliance rate is calculated by dividing fully documented compliant work packages by total work packages completed. Only the 198 work packages with full sustainability documentation count as compliant. The 18 pending assessments cannot be counted until approved, and the 24 grandfathered work packages, while legally acceptable, do not meet current sustainability criteria for compliance reporting. Calculation: 198 compliant / 240 total = 0.825 or 82.5%. This result falls below the required 85% threshold, creating a compliance threat that Lucía must address proactively by accelerating documentation completion for pending assessments or identifying additional work packages that can achieve compliance status. The scenario tests the ability to apply compliance calculation criteria correctly when faced with multiple work package categories and ambiguous situations, which is critical for managing regulatory requirements in contemporary projects with sustainability mandates.

**Why not A:** The 85.0% figure appears to meet the regulatory threshold exactly, but this calculation is incorrect because it inappropriately counts some non-qualifying work packages. Arriving at 85% would require including either the 18 pending assessments or some portion of the grandfathered work packages—both of which the compliance office has explicitly stated do not qualify for the 85% threshold. This answer represents the target threshold rather than the actual calculated result.

**Why not C:** The 90.0% figure would result from dividing the 198 fully documented work packages by only the 220 packages that are either compliant or pending (198 ÷ 220 = 90%), incorrectly excluding the 24 grandfathered packages from the denominator. The compliance rate must be calculated against all 240 completed work packages regardless of their compliance category, as these represent the full universe of work the project has executed.

**Why not D:** The 92.5% figure would result from dividing 198 compliant packages by only the 214 packages that are either pending or compliant (198 ÷ 214 ≈ 92.5%), a denominator that excludes both the grandfathered exceptions and some other category. This calculation reduces the denominator inappropriately, inflating the apparent compliance rate and masking the project's actual shortfall against the 85% regulatory requirement.

Key Concept

This question covers Confirm Compliance Requirements under Plan and Manage Project Compliance (Business Environment).