PMP Practice: Confirm Compliance Requirements
Question 1 of 6 in Plan and Manage Project Compliance
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: 82.5%
Explanation
The compliance rate is calculated by dividing fully documented compliant work packages by total work packages completed. Only the 198 work packages with full sustainability documentation count as compliant. The 18 pending assessments cannot be counted until approved, and the 24 grandfathered work packages, while legally acceptable, do not meet current sustainability criteria for compliance reporting. Calculation: 198 compliant / 240 total = 0.825 or 82.5%. This result falls below the required 85% threshold, creating a compliance threat that Lucía must address proactively by accelerating documentation completion for pending assessments or identifying additional work packages that can achieve compliance status. The scenario tests the ability to apply compliance calculation criteria correctly when faced with multiple work package categories and ambiguous situations, which is critical for managing regulatory requirements in contemporary projects with sustainability mandates.
**Why not A:** The 85.0% figure appears to meet the regulatory threshold exactly, but this calculation is incorrect because it inappropriately counts some non-qualifying work packages. Arriving at 85% would require counting 204 of the 240 packages as compliant—that is, including some of the pending assessments or grandfathered work packages—both of which the compliance office has explicitly stated do not qualify for the 85% threshold. This answer represents the target threshold rather than the actual calculated result.
**Why not C:** The 90.0% figure would result from counting the 18 pending assessments as compliant ((198 + 18) ÷ 240 = 216 ÷ 240 = 90%). The compliance office has explicitly stated that pending assessments do not qualify as compliant for reporting purposes, however likely their approval may be. The compliance rate must be calculated against all 240 completed work packages regardless of their compliance category, as these represent the full universe of work the project has executed, with only fully documented packages counted as compliant.
**Why not D:** The 92.5% figure would result from counting the 24 grandfathered work packages as compliant ((198 + 24) ÷ 240 = 222 ÷ 240 = 92.5%). Although grandfathered exceptions are legally permitted, the compliance office has stated they do not qualify as compliant for reporting purposes. This calculation inflates the numerator inappropriately, inflating the apparent compliance rate and masking the project's actual shortfall against the 85% regulatory requirement.
Key Concept
This question covers Confirm Compliance Requirements under Plan and Manage Project Compliance (Business Environment).