PMP Practice: Analyze Consequences of Noncompliance
Question 4 of 6 in Plan and Manage Project Compliance
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Issue a change request to update the ventilation system specifications to meet the new regulations, including cost and schedule impact analysis, and present it to the change control board for approval
Explanation
When a compliance gap is identified that affects regulatory requirements, the project manager must immediately initiate formal change control to address it. The scenario establishes that the sponsor has made regulatory compliance non-negotiable and that violations could suspend the facility's operating license—this eliminates any option that delays compliance action. A change request with full impact analysis allows the change control board to make an informed decision about proceeding with the necessary specification updates, absorbing the restocking fee, and adjusting schedule and budget accordingly. This follows proper governance while ensuring the project delivers a compliant facility. The predictive approach requires documented change control for any baseline modifications, and compliance requirements are mandatory constraints that override cost and schedule preferences.
**Why not A:** Simply logging the compliance gap as a risk and scheduling a cost-reduction meeting does not initiate the formal change control process that a predictive project requires when a baseline must be changed. The risk register is for tracking; it does not authorize design changes, and "exploring cost-reduction strategies" implies trying to avoid the required upgrade rather than properly addressing it.
**Why not B:** Requesting a regulatory variance before even formally analyzing the change or presenting it to the change control board is premature and potentially counterproductive. A variance is not guaranteed, the sponsor has stated compliance is non-negotiable, and pursuing a variance as a first step delays the formal project response while creating an impression that the team is seeking workarounds rather than addressing the issue directly.
**Why not C:** Proceeding with the original non-compliant equipment order while awaiting a legal review places the project at direct regulatory risk, which the sponsor has explicitly called out as unacceptable. If the legal review concludes that the regulations do apply—a highly probable outcome given they have already taken effect—the project will have already incurred deeper costs and schedule impact. This option prioritizes short-term convenience over clear compliance obligations.
Key Concept
This question covers Analyze Consequences of Noncompliance under Plan and Manage Project Compliance (Business Environment).