PMP Practice: Balance competing resource demands
Question 5 of 5 in Plan and Manage Budget and Resources
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Conduct a retrospective with the development team to identify what led to the reduced velocity and unplanned work, then review the findings with the product owner to realign priorities and budget expectations for future iterations
Explanation
In a hybrid project using iterative development, when budget variance occurs alongside reduced velocity and scope changes, the project manager should first understand the root cause before taking corrective action. Conducting a retrospective allows the team to openly discuss what happened—why velocity dropped and how unplanned features entered the iteration without proper prioritization. This creates transparency and enables collaborative problem-solving. Following up with the product owner ensures alignment on backlog management and prevents similar issues in future iterations. This approach addresses both the budget variance and the underlying process breakdown, which is essential in adaptive work where the team must continuously inspect and adapt. The scenario's closing fact—that this happened mid-project with another iteration starting in three days—makes understanding and correcting the process the clear priority before committing to the next iteration.
**Why not B:** Requesting additional budget treats the symptom rather than the cause and does not address why velocity dropped or how unplanned work entered the iteration. Extending iteration length fundamentally changes the agreed cadence without understanding whether that would actually solve the problem. This reactive approach bypasses the governance process for managing budget variations.
**Why not C:** Removing completed work is not feasible once features are integrated and potentially deployed. This approach ignores the fact that effort was already expended and does not address why the unplanned work was accepted in the first place. It also damages trust with the product owner and team by unilaterally reversing decisions rather than collaboratively addressing the process failure.
**Why not D:** Updating the cost baseline without investigating the cause assumes the variance is permanent and acceptable. This approach fails to address whether the reduced velocity and unplanned scope additions represent a systemic problem or a one-time event. It bypasses the opportunity to correct course and potentially lets process breakdowns continue unchecked into future iterations.
Key Concept
This question covers Balance competing resource demands under Plan and Manage Budget and Resources (Process).
This is 1 of 100 free PMP questions
Unlock 6,300+ PMP practice questions with detailed explanations, progress tracking, and exam readiness prediction.
Unlock All Questions