Skip to content
PMPEasy

PMP Practice: Execute change management strategy according to the methodology

Ash Okonkwo is managing a warehouse automation project for Swift Ridge Labs. During month 5, the sponsor requests that three additional conveyor belt systems be added to the scope. The change control board approves the request. The original project had a budget at completion (BAC) of $850,000 and was scheduled for 10 months. At the time of the approved change, the project has spent $380,000 and completed work valued at $425,000. The approved change will add $180,000 to the budget and extend the timeline by 2 months. What is the new budget at completion (BAC) after incorporating this approved change?

Key Concept

This question covers Execute change management strategy according to the methodology under Manage Project Changes (Process).

This is 1 of 100 free PMP questions

Unlock 6,300+ PMP practice questions with detailed explanations, progress tracking, and exam readiness prediction.

Unlock All Questions