PMP Practice: Implement Resolution Strategies

Question 8 of 10 in Manage Conflicts

Pick an answer below — you'll get the explanation instantly, no signup.

Marisol Santos-Reyes is facilitating the sprint retrospective for her agile team at Lagom Games, a mobile game development studio. During the retro, two senior developers—Mateo and Ingrid—begin a heated argument. Mateo insists the team should focus exclusively on new features to meet the roadmap commitments made to stakeholders. Ingrid argues the team must allocate at least 30% of capacity to refactoring technical debt, which has accumulated over the past four sprints. Both developers are visibly frustrated, and other team members are becoming uncomfortable. The team's velocity has dropped 25% over the last two sprints, and the product owner has expressed concern about missing the upcoming release milestone. Which approach would be MOST effective for managing this conflict?
Show answer & explanation

Correct answer: Facilitate a focused discussion to help the team understand how technical debt is affecting velocity and collaborate on a sustainable balance between new features and refactoring

Explanation

The conflict between Mateo and Ingrid stems from a deeper systemic issue: the team has not transparently discussed how accumulated technical debt is impacting their ability to deliver value. The 25% velocity drop is a warning signal that the team's technical foundation is eroding. The most effective approach is to help the team see the connection between technical health and sustainable delivery, then collaboratively decide on a path forward. This addresses the root cause of the conflict rather than suppressing it or imposing a solution. In agile environments, the team is empowered to self-organize around sustainable practices, and the retrospective is precisely the forum for surfacing and resolving these tensions. By facilitating a data-informed discussion, the project manager helps the team make an informed decision that balances immediate delivery pressure with long-term capability.

**Why not A:** Proposing a 15% compromise by splitting the difference does not address the underlying issue. An arbitrary midpoint between two positions may not reflect the actual technical debt impact on velocity or the real feature delivery needs. Effective resolution requires understanding the root cause, not mechanical compromise.

**Why not B:** Asking both developers to take the discussion offline dismisses the conflict rather than addressing it. The retrospective is precisely the right forum for discussing process and technical concerns, and redirecting the conversation away from this venue signals that the team should avoid difficult topics.

**Why not D:** Escalating the prioritization decision to the product owner removes the team's involvement in understanding and solving the problem. The product owner can decide backlog order, but the team needs to collectively understand how technical debt is affecting their velocity to make sustainable commitments going forward.

Key Concept

This question covers Implement Resolution Strategies under Manage Conflicts (People).