Skip to content
PMPEasy

PMP Practice: Interpret the source and stage of the conflict

Question 1 of 4 in Manage Conflict

Pick an answer below — you'll get the explanation instantly, no signup.

Xiu-Ying Huang is managing a solar farm installation project for Astrid Lindqvist-Holm Partners across three rural counties. The engineering lead, Ishaan Goswami, insists on using premium-grade inverters that exceed specifications, citing long-term reliability. The procurement manager, Rowan Fitzgerald-Yamamoto, strongly opposes this choice because it will push the project 18% over budget and delay delivery by five weeks. Both stakeholders have sent escalating emails to Xiu-Ying and are now refusing to attend joint planning sessions. Xiu-Ying has verified that both the premium and standard inverters meet all contractual and safety requirements. What should Xiu-Ying do to manage this conflict?
Show answer & explanation

Correct answer: Schedule individual meetings with Dante and Lila to understand each person's underlying concerns and priorities before facilitating a joint discussion

Explanation

When conflict arises between stakeholders, the project manager should first analyze the context by understanding each party's underlying concerns, interests, and motivations. Dante's insistence may stem from quality concerns, past equipment failures, or professional reputation considerations. Lila's opposition likely relates to budget accountability, organizational policies, or competing resource demands. By meeting individually first, Xiu-Ying creates a safe space for each stakeholder to express concerns fully without the pressure of defending positions publicly. This diagnostic step provides essential information before attempting resolution. Once Xiu-Ying understands the root causes, she can facilitate a collaborative discussion focused on interests rather than positions, potentially identifying creative solutions such as phased inverter upgrades, warranty extensions, or value engineering in other areas. This approach demonstrates servant leadership and treats the conflict as an opportunity to strengthen stakeholder relationships while finding the best outcome for the project.

**Why not B:** While reviewing project documentation is useful, immediately making a unilateral decision based solely on original specifications ignores the stakeholders' concerns and fails to explore whether the project context has changed since baseline approval. This approach may technically resolve the immediate dispute but damages relationships and misses opportunities for collaborative problem-solving. The project manager should understand stakeholder perspectives before defaulting to baseline documents.

**Why not C:** Escalating to the sponsor is premature because the project manager has not yet attempted to understand or resolve the conflict. While budget variances may eventually require sponsor involvement, effective conflict management begins with the project manager analyzing the situation and facilitating stakeholder communication. Immediate escalation signals an inability to manage stakeholder relationships and wastes sponsor time on issues the project manager should handle. The scenario provides no indication that organizational policy requires sponsor approval at this stage.

**Why not D:** Making a unilateral decision without first understanding each stakeholder's concerns bypasses essential conflict resolution steps and risks creating long-term relationship damage. While staying within budget is important, the project manager has not explored whether creative solutions exist that might address both quality and cost concerns. This approach treats the conflict as purely technical when it fundamentally involves stakeholder relationships and requires collaborative problem-solving. The decision may be technically defensible but fails to leverage the expertise and buy-in of key team members.

Key Concept

This question covers Interpret the source and stage of the conflict under Manage Conflict (People).

Share:

This is 1 of 100 free PMP questions

Unlock 6,300+ PMP practice questions with detailed explanations, progress tracking, and exam readiness prediction.

Unlock All Questions