PMP Practice: Communicate Change Status
Question 3 of 8 in Manage and Control Changes
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: 0.96
Explanation
The cost performance index (CPI) measures cost efficiency by comparing the value of work completed to the actual cost incurred. The formula is CPI = Earned Value (EV) ÷ Actual Cost (AC). From the scenario: EV = $264,000 (value of work completed) and AC = $276,000 (actual expenditure). Therefore, CPI = $264,000 ÷ $276,000 = 0.96 (rounded to two decimal places). This indicates the project is spending approximately $1.04 for every dollar of value delivered, meaning cost performance is slightly under target. Understanding the current CPI is essential before proposing the change because the change control board needs to assess whether adding $72,000 to a project already experiencing cost overruns is financially sustainable. In a hybrid environment, financial governance remains critical even when using adaptive approaches for portions of the work, and baseline performance metrics inform change approval decisions.
**Why not A:** A CPI of 1.15 would indicate the project is delivering $1.15 of value for every dollar spent—a cost-favorable position. This could result from inverting the formula and dividing actual cost by earned value ($276,000 ÷ $264,000 ≈ 1.045) or from using incorrect figures entirely. The project has spent more than it has earned in value, so a CPI above 1.0 is inconsistent with the scenario data and would give the change control board a falsely optimistic picture of financial performance.
**Why not C:** A CPI of 0.87 would indicate more severe cost overperformance than the data supports, suggesting the project is only delivering $0.87 of value per dollar spent. This could result from confusing the earned value with the planned value (PV = $240,000 ÷ AC = $276,000 ≈ 0.87), which compares what was planned to be done against what was spent rather than what was actually accomplished against what was spent. Using PV instead of EV misapplies the earned value formula.
**Why not D:** A CPI of 1.10 is directionally incorrect—it implies cost efficiency above 1.0, meaning the project is under budget on a per-unit-of-value basis, which contradicts the scenario where actual costs ($276,000) exceed earned value ($264,000). This figure might arise from applying an incorrect ratio, perhaps dividing the planned value by earned value or making a computational error that inverts the relationship between spending and value delivery.
Key Concept
This question covers Communicate Change Status under Manage and Control Changes (Business Environment).
This is 1 of 100 free PMP questions
Unlock 6,300+ PMP practice questions with detailed explanations, progress tracking, and exam readiness prediction.
Unlock All Questions