PMP Practice: Assess consolidated project plans for dependencies, gaps, and continued business value
Question 2 of 5 in Integrate Project Planning Activities
Show answer & explanation
Correct answer: Use a predictive planning approach with detailed phase-by-phase planning, comprehensive documentation, and formal change control aligned to contract requirements
Explanation
This project has every characteristic that demands a predictive approach: fixed-price contract with defined milestones, extensive regulatory compliance requirements, mandatory detailed documentation, and severe penalties for specification deviation. The regulatory agency's explicit warning about re-certification delays makes flexibility a liability rather than an asset. Integrated project planning here means aligning the planning approach to the project's constraints and success criteria. A predictive lifecycle with comprehensive upfront planning, detailed schedules, and rigorous change control processes directly supports the contract terms and regulatory framework. The team member's suggestion, while well-intentioned, fails to account for the project's context where requirements are fixed by regulation and contract law, not subject to iterative discovery.
**Why not A:** Implementing agile sprints with extra documentation ceremonies contradicts the project's fundamental constraints. Fixed-price milestones, regulatory compliance gates, and the threat of a six-month re-certification process all require predictable, plan-driven execution. Adding documentation to agile ceremonies does not address the structural incompatibility.
**Why not B:** Starting with predictive planning and then evaluating an agile transition introduces unnecessary risk. The project has clear, fixed requirements, regulatory constraints, and contractual obligations that make predictive planning appropriate throughout. Switching methodology mid-project could trigger the re-certification process the regulatory agency warned about.
**Why not C:** A hybrid approach with sprints for development and phase gates for regulatory reviews still introduces iterative scope changes into a project where any deviation triggers a six-month re-certification delay. The regulatory agency has explicitly stated that specification deviations are unacceptable, making iterative development inappropriate regardless of the governance overlay.
Key Concept
This question covers Assess consolidated project plans for dependencies, gaps, and continued business value under Integrate Project Planning Activities (Process).