Skip to content
PMPHard

PMP Practice: Support the team to subdivide project tasks as necessary to find the minimum viable product

Question 3 of 4 in Execute Project with the Urgency Required to Deliver Business Value

Pick an answer below — you'll get the explanation instantly, no signup.

Emilio Castañeda-Solis is managing a hybrid project for Caldera Space Systems to develop a machine learning platform for small businesses. The team spent five sprints building sophisticated data visualization features, automated reporting dashboards, and advanced analytics capabilities. At the recent sprint review, the product owner expressed frustration that none of the core data ingestion functionality works reliably — businesses cannot even upload their data files without errors. The product owner states: 'We have beautiful dashboards showing no data. Our pilot customers are canceling because they can't get started.' The development team explains they assumed data ingestion was straightforward and focused on the 'exciting' features first. The project is now three months behind schedule and stakeholders are questioning the team's approach. What should Emilio have done earlier to prevent this situation?
Show answer & explanation

Correct answer: Facilitated a collaborative session with the team and product owner to identify and sequence features by dependency and business value, ensuring foundational capabilities were prioritized before advanced features

Explanation

In a hybrid approach focused on delivering minimum viable product, the project manager's role includes helping the team understand feature dependencies and business value to guide effective prioritization. The scenario reveals a fundamental breakdown: the team built advanced features without ensuring the foundational capability (data ingestion) worked first. This is a classic failure to identify and build toward a true minimum viable product. The project manager should have facilitated collaborative discussions early in the project where the team and product owner worked together to understand feature dependencies, define what constitutes minimum viability, and sequence work so that foundational elements were completed before dependent features. This collaborative approach respects team self-organization while ensuring everyone understands the logical build sequence and what creates actual business value. The closing fact — that the team 'assumed data ingestion was straightforward and focused on the exciting features first' — indicates this was a shared understanding problem, not a technical documentation or authority issue, making facilitated collaboration the appropriate preventive measure.

**Why not A:** Establishing a rigorous change control process to prevent the team from selecting lower-priority work addresses governance but not the understanding gap. The team did not deliberately choose wrong items through a broken change process; they assumed foundational work was straightforward and focused on exciting features. The root cause was misunderstanding dependencies, not lack of process controls.

**Why not B:** Requiring detailed technical specifications before sprint work began imposes a waterfall-style documentation phase on a hybrid project. This contradicts the adaptive execution model and would delay delivery without necessarily ensuring the team understood feature dependencies and business value sequencing.

**Why not C:** Assigning a technical architect to make all prioritization decisions removes team ownership and contradicts agile self-organization principles. The PM's role is to facilitate shared understanding of priorities and dependencies, not to install a single decision-maker who dictates work order to the team.

Key Concept

This question covers Support the team to subdivide project tasks as necessary to find the minimum viable product under Execute Project with the Urgency Required to Deliver Business Value (Process).

Share:

This is 1 of 100 free PMP questions

Unlock 6,300+ PMP practice questions with detailed explanations, progress tracking, and exam readiness prediction.

Unlock All Questions