PMP Practice: Support the team to subdivide project tasks as necessary to find the minimum viable product
Question 3 of 4 in Execute Project with the Urgency Required to Deliver Business Value
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Facilitated a collaborative session with the team and product owner to identify and sequence features by dependency and business value, ensuring foundational capabilities were prioritized before advanced features
Explanation
In a hybrid approach focused on delivering minimum viable product, the project manager's role includes helping the team understand feature dependencies and business value to guide effective prioritization. The scenario reveals a fundamental breakdown: the team built advanced features without ensuring the foundational capability (data ingestion) worked first. This is a classic failure to identify and build toward a true minimum viable product. The project manager should have facilitated collaborative discussions early in the project where the team and product owner worked together to understand feature dependencies, define what constitutes minimum viability, and sequence work so that foundational elements were completed before dependent features. This collaborative approach respects team self-organization while ensuring everyone understands the logical build sequence and what creates actual business value. The closing fact — that the team 'assumed data ingestion was straightforward and focused on the exciting features first' — indicates this was a shared understanding problem, not a technical documentation or authority issue, making facilitated collaboration the appropriate preventive measure.
**Why not A:** Establishing a rigorous change control process to prevent the team from selecting lower-priority work addresses governance but not the understanding gap. The team did not deliberately choose wrong items through a broken change process; they assumed foundational work was straightforward and focused on exciting features. The root cause was misunderstanding dependencies, not lack of process controls.
**Why not B:** Requiring detailed technical specifications before sprint work began imposes a waterfall-style documentation phase on a hybrid project. This contradicts the adaptive execution model and would delay delivery without necessarily ensuring the team understood feature dependencies and business value sequencing.
**Why not C:** Assigning a technical architect to make all prioritization decisions removes team ownership and contradicts agile self-organization principles. The PM's role is to facilitate shared understanding of priorities and dependencies, not to install a single decision-maker who dictates work order to the team.
Key Concept
This question covers Support the team to subdivide project tasks as necessary to find the minimum viable product under Execute Project with the Urgency Required to Deliver Business Value (Process).